Project Activities and Milestones

Establishing the project

Milestone Who Target Date Status Comments
Establish project portal on WikiResearcher Wayne Mackintosh and Carina Bossu 23 December 2010 Complete
  • Populate landing page
  • Complete "About" page
  • Establish planning page
  • Import wiki versions of project documentation
Establish communication strategies Carina Bossu 23 December 2010 Complete
  • Set up discussion lists for the project
  • Specify virtual communication technologies and communication schedule
  • Does the project need separate lists for different audiences?
  • Ensure that discussion list tool provides rss feed for the project portal page.
Confirm project teams Carina Bossu 23 December 2010 Complete
  • Confirm names and participation of:
    • Project team
    • Reference group
    • Develop role statements/responsibilities for each group
Establish project plan in WikiResearcher Carina Bossu 20 January 2011 Complete
  • Require a project plan mapped to the activities, outputs and outcomes with target dates for the evaluation plan.
Develop risk management plan Carina Bossu 20 January 2011 Complete
Refine dissemination plan and specified target outputs Carina Bossu 20 January 2011  Complete
  • The evaluation plan requires a dissemination matrix / table identifying each dissemination vehicle, intended target audience and anticipated numbers / targets for specifying KPIs.
Develop monitoring and evaluation plan Wayne Mackintosh 15 December 2010 Complete
  • Develop and refine logic model
  • Refine output/outcome statements
  • Specify KPIs and verifiable data

Phase 1: Investigation

Milestone Who Target Date Status Comments - Breakdown Activities - Responsibilities
Organise the first face-to-face meeting with team members Carina Bossu 30/01/2011
Complete
  • Send a reminder to all team members by 20/01/2011
  • All members have been notified and agreed with the date and time of the meeting
  • Confirm the venue and its facilities by 20/01/2011
Employ a project manager Carina Bossu 01/03/2011
Complete
  • Debbie Bridge has worked for DEHub since its early stages and her performance has been outstanding. Her CV will be sent to all members for approval. The employment of the project manager will be also discussed during the meeting on 14 Feb 2011
Agree detailed Project Plan, including the mission and goals Team members 14/02/2011
Complete
  • The project plan will be available on Wikiresearcher for consultation and feedback prior the meeting. The final project plan will be further discussed and agreed at the first face-to-face meeting by the research team.
Agree detailed Project Evaluation Plan Wayne Mackintosh 14/02/2011
Complete
  • The Evaluation Plan will be available on Wikiresearcher for consultation and feedback prior the meeting. The Evaluation Plan will be further discussed and agreed at the meeting. Wayne Mackintosh will be participating to the meeting via Skype.
Meet the research team group via Skype or teleconference Team members 07/03/2011
Confirmed
  • This date will be confirmed at the meeting on 14 Feb 2011
Abstract Deadline of the 24th ICDE Conference in Bali - Indonesia
Carina and team members
31/03/2011
Complete
  • It was decided by the group that Carina will start the abstract and send to team members for feedback and comments. The research team decided to withdrawn from this conference because nobody will be able to attend it. David Bull offfered to attend and present. Paper was not withdrawn.
Poster to Ed-Media in Portugal
Carina, Mark and David
12/04/2011
Complete
  • It was decided by the group that Carina will start drafting the poster and seek feedback and contributions from the team members.
Contact the reference group by email Carina Bossu and Reference Group Members 30/05/2011
Complete
  • Send an email to members of the reference group to collect their feedback on the progress of the project and also on the survey instrument already in Qualtrics.
Ethics Application developed and approved Carina Bossu 30/04/2011
Complete
  • First draft sent to members on 30th March 2011
  • Final ethics application and supporting documents sent to HDR Ethics Committee on 2nd May. Approved 10 May 2011.
Finalise the Annotated Bibliography Team members 30/09/2011
Complete
  • The completion of this task will meet Objective 1 of this project.
Develop and pilot data collection instruments (survey and interviews) Team members
30/06/2011
Complete
  • The draft of the instruments were developed by Carina and sent to team members for feedback. Feedback and suggestions from team members and also from the evaluator and other experts were incorporated in the survey and interview instruments.
  • We have now to develop the survey in Qualtrics and send it for piloting.
ALTC - Progress Report Carina Bossu and Project Manager
02/05/2011
Complete
  • Progress report will be sent to team members for feedback and suggestions.
Ascilite - call for abstracts for papers
Carina and project team
13/05/2011
Cancelled
  • 14 – 29 May 2011 - Abstracts in review
  • 30 May 2011 - Notification to authors of abstract acceptance for papers
  • Full paper submission on 26 June 2011.
  • Final submission cancelled due to other commitments.
Establish the sample of participants for data collection Team members 30/06/2011
Complete
  • The completion of this milestone will require the assistance of all project members, including the reference group.
  • Members will provide references and names of potential participants.
  • Purposeful sampling strategy will be used.
Send the online survey to participants Team members
4/07/2011
Complete
  • Carina will also develop the online survey tool.
  • Data collected will be a combination of quantitative and qualitative information.
  • Meet Objective 2 of the project.
Select the sample of participants for interviews Team members 30/07/2011
Complete
  • Survey participants will be asked if they wish to be interviewed and/or to participate in focus groups if they wish.
ICDE - Full paper submission
David and members
01/07/2011
Complete
  • 31 May Abstract Accepted
  • Full paper due on 1st August
Conduct interviews Carina Bossu 30/9/2011
Complete
  • Interviews will be conducted via telephone.
  • Data collected from interviews will be primarily qualitative
Transcribe interviews Debbie 30/9/2011 Complete
  • All interviews were sent to a private company to be transcribed.
Submission to Journal of Open, Flexible and Distance Learning Carina Bossu 31/8/2011 Complete
  • Article Submission in by 31 August 2011
Finalise preliminary data analysis Carina Bossu 02/09/2011
Complete
  • Data will be analysed as data collection progresses.
  • NVivo9, will be used to support the researchers during the analysis phase of this study. There is also a possibility to use an open source software to assist the data analysis.
  • Thematic analysis will be conducted.
Paper proposal for Special Edition of Distance Education journal Carina Bossu and Mark Brown 09/09/2011 Complete
  • Confirmation October 2011
  • Full paper Oct/Nov 2011
Second face-to-face meeting with team members and evaluator
Carina Bossu
15/09/2011
Complete
  • Discuss the possibility of this meeting on 14 Feb 2011
  • The Purpose of the meeting will be to finalise Stage 1 and to plan Stage 2
  • Carina and the Project Manager will organise it.
  • All team members are required to attend.
  • The evaluator could participate via Skype.
  • Date set for 15 September 2011 in Armidale
Year 1 (Stage 1) Project Report
Carina Bossu and Project Manager
01/11/2011
Complete
  • Progress report will be sent to team members for feedback and suggestions.


Phase2: Development, evaluation and dissemination

Milestone Who Target Date Status Comments - Breakdown Activities - Responsibilities
Send interview transcript back to the participants for validation

Carina Bossu and

Project Officer

Nov 2011
Complete
  • This process will assist to build rapport and enable validation of findings
  • Preliminary analysis will be sent to participants by email
  • Participants will be provided with a timeframe to respond. If they do not respond to the email by Jan 2011 the researchers will assume they were satisfied with the analysis
  • The additional comments on the analysis will be treated as additional data
OCWC/OER 2012 Conference, Cambridge
Carina Bossu
16-20 April 2012
Cancelled

Finalise Submission for the Journal of Distance Education Special Issue on OER
Team
30 April 2012
Complete
  • Paper submitted on 13th Jan
  • Reviewers' comments submitted on 16th March
  • Copy editing comments submitted on 30th April
Send preliminary data analysis to the reference group to collect their feedback
Carina Bossu
30 May 2012
Complete
  • This process will enable validation of findings
  • Preliminary analysis will be sent to the reference group by email
  • Reference group members will be asked to provide feedback on the findings
ALTC – Progress Report
Team
01 June
Complete

EDEN Conference, Porto
Mark Brown
6-9 June
Cancelled

Ascilite Conference, New Zealand
Team
15 June
Complete
  • Friday 15 June 2012 - Deadline for submission of full and concise papers & symposium
  • 16 August 2012 - Completed reviews sent back to authors
  • 30 September 2012 - Deadline for submission of revised papers
  • 30 September 2012 - Early bird registrations close
  • Conference will be held from 25 to 28 November 2012 - http://www.ascilite.org.au/index.php?p=conference
Finalise data analysis
Team
30 July
Complete
  • The team will include the research participants' additional feedback on the transcript
  • The feedback and suggestions from the reference group will be treated as additional data and incorporated in the analysis.
Draft the Feasibility Protocol
Team
30 July
Complete
  • The team members will work together on drafting the protocol
  • The draft will be sent to the symposium participants 3 weeks before the event. This will hopefully allow them enough time to read it and be prepared to provide us their insight.
Conclusion of four short examples of OER practice
Team
 30 July
Complete
  • The case studies were chosen by the project team: Athabasca University - Canada, OpenLearn project from Open University - UK, Otago Polytechnic - NZ and Universitat Oberta de Catalunya - Spain
  • The case studies were analysed and written by a research assistance (Dr Frances Gray)
  • Then reviewed by the project team and included as part of the Feasibility Protocol
Third face-to-face meeting with team members and evaluator
Team
30 Aug
Complete
Discuss the project progress and final details of the Symposium
Conduct the Symposium
Team
31 Aug
Complete
This is a major project activity and will have a specific planning chart for it. The completion of this Milestone will meet Objective 3 of this project.
Incorporate additional feedback collected during the symposium into the findings
Team
30 Sept
Complete
With the assistance of team members
Fourth face to face meeeting with team member
Team
5 Oct
Complete
To finalise the report and feasibility protocol
Final version of the Feasibility Protocol
Team 30 Oct Complete The completion of this Milestone will meet Objective 4 of this project.
Final evaluation report
Wayne Mackintosh
Oct 2012
Complete
This will deliver the project's Output 4.
OLT Final Report Narrative
Team 14/12/2012
Complete
The final report was submit to OLT on 14th Dec. The project team has been waiting for OLT feedback and approval on the report. Then, the report will be disseminate.
Final Financial Report
Team
12/04/2013
Complete
Sue Watson (project officer) has been working on the financial report


Our Communication Plan

Purpose

A central purpose is to ensure that those interacting with this research project are reliably informed and engaged with issues concerning the scope of project activities, deliverables and their possible consequences. The strategy should ensure that messages, reports, communications tools and events are utilised and programmed into the operations of the project. It is expected that everyone involved within the project should act as an agent for dissemination and communication. It is hoped that this document will assist project members by providing opportunities for engagement and communication.

Procedures

Communication carried out by the Research Team members:

  • Formal means of communication:
    • Monthly meetings via videoconference or telephone (establish on 14th Feb 2011)
    • Two face-to-face meetings per year (4 in total)
    • Updates via Google group to all team members
    • Minutes of the meetings
    • ALTC reports
    • Evaluation reports
    • WikiResearcher
  • Informal communication:
    • Emails and telephone calls amongst members

Communication carried out by the Reference Group members:

  • Formal communication:
    • Individual emails and if desired skype calls for feedback/input
    • Possibly one face-to-face meeting at the symposium
    • Year 1 and final ALTC reports
    • Evaluation reports
    • WikiResearcher
  • Informal communication:
    • Emails and telephone calls amongst members

Tools

  • For the monthly videoconference meeting, the preferred tool will be Skype. The second option will be to use teleconference equipment, where team members will be provided with the telephone number to call.
  • The face-to-face meetings will be organised in advance by the research team. The first one will be held in Sydney on 14th February 2011 from 2:00pm to 4:00pm.
  • Informal communication will require telephone calls and standard electronic mail.
  • WikiResearcher will be the official website of the project and the place where the project updates and progress will be available for the team members and reference group.
  • Google group and Rss feed
  • Reports and minutes of the meetings will be developed in Word and emailed to individuals.

Stakeholder Identification

There is a diverse range of stakeholders that could be affected by this project, ether by project process or by project results.

The stakeholders directly affected by the project process are the project team members.

The key group of stakeholders that will be potentially affected by the project results in the short term are:

  • University PVC(A)s and Associate Deans concerned with learning and teaching: The project will have a positive impact on social inclusion strategies through the use, re-use and distribution of content materials. By showcasing their educational materials by means of OERs, institutions can attract new students, increase the development of new learning materials, stimulate internal innovation and improve learning and teaching.
  • Decision-makers involved in developing institutional policies and strategies across the higher education sector in Australia: Provision of a useable, relevant and pragmatic protocol for the adoption, use and management of OERs based on national and international perspectives of current and potential users in relation to the effective use of OERs in higher education.
  • Government: Meet the current political agenda to expand access to learning for learners from all walks of life, promote life-long learning and wide participation in higher education through policy recommendations for HE institutions in Australia regarding the adoption, use and management of OERs.

In the long-term, the stakeholders that will be potentially affected by the project results will be:

  • Academic staff involved in the adoption and development of OERs in HE institutions.
  • Educational designers and other staff who are engaged in supporting the integration of OERs into learning and teaching practice.
  • Learners participating in distance and online learning programs or in any other formal, informal and non-formal learning activities.


Reporting

Within the Project Team

Monthly meetings with the research team will present the opportunity for team members to report to each other on the project activities and progress. Tied in with the monthly team meetings is a summary of the meetings that will be available on WikiResearcher to all team members, the reference group and the project evaluator for access and contributions.

Emails, RSS Feed and Google group can also be used by members as a way of keeping in contact and reporting to each other on project activities being undertaken.

Management Reporting

The official reports required by ALTC are:

  • 02/05/2011 – Progress Report
  • 01/11/2011 – Year 1 (Stage 1) Project Report
  • 01/05/2012 – Progress Report
  • 01/11/2012 – Final Report Narrative
  • 04/02/2013 – Final Financial Report

The project reports will be developed by the Project Manager with the assistance of the research team. The final report will also include the evaluation report.

Given that this is a project about OERs, we have a strategic advantage in being able to use an open collaborative model for the design and development of the project and evaluation plan. The research reports, materials and outputs will be released under Creative Commons Attribution (CC-BY) license. This will increase return on investment for the funders and participants. We will also use a wiki model for the planning, execution and dissemination of the findings through open access journals.


Communication Action Plan

There are a number of engagement and communication methods required and available to the project team to deliver the key messages and disseminate progress on the project activities. With the Communication Strategy, there is a need to formulate an action plan that can be incorporated into the main project plan so that all engagement and communication tasks are allocated and actionable. The following table identifies the frequency, likely communication points and methods to be employed when communicating with key stakeholders.

ONB = On a needs basis



Key Stakeholders
Method
Chief Researcher
Research Team
Reference Group
Project Manger
Evaluator
Symposium Facilitator
ALTC
PVC(A)s
Deans
Gov.
Face-to-face meetings
4x
4x
N/A
4x
Assist
N/A


Videoconference meetings
Monthly
Monthly
ONB
Monthly
Monthly
N/A


WikiResearcher
ONB
ONB
ONB
ONB
ONB
N/A


Minutes meeting
Receive
Receive
N/A
Responsible
Receive
N/A


Conferences
Join
Join
N/A
N/A
Join
N/A


ALTC Reports
Assist
Assist
Receive major
Assist
Provide feedback
Receive
Receive
Receive
Google Groups
Assist
Assist
Provide feedback
Assist
Assist
Receive


RSS Feed
ONB
ONB
Receive
ONB
ONB
Receive


Email
ONB
ONB
ONB
ONB
ONB
ONB


Phone
ONB
ONB
ONB
ONB
ONB
ONB


Symposium
Assist
Assist
Provide feedback
Assist
Provide feedback
Assist
Invite
Invite


Dissemination activities

Phase 1

Proposed Publications

  • Book chapter (1)
  • Journal article (2) - eg. British Journal of Educational Technology (BJET) with submission of manuscripts by late May 2011 and/or Australasian Journal of Educational Technology (AJET) with submission of manuscript by August 2011

Proposed Conference Presentations

  • Australian Council on Open and Distance e-Learning (ACODE), ACODE 54 Workshop on “Open Educational Resources”, Palmerston North (NZ) on 11 November 2010 (Carina)
  • 6th Pan-Commonwealth Forum on Open Learning (PCF6), Titled “Access and Success in Learning: Global Development Perspectives”, Kochi (India) from 24 to 28 November 2010 (Carina)
  • Education 2011 to 2021- Global challenges and perspectives of blended and distance learning, Sydney from 15 to 18 February 201(Carina)
  • ED-MEDIA 2011-World Conference on Educational Multimedia, Hypermedia & Telecommunications, Lisbon (Portugal), from June 27 to July 1, 2011 (Mark Brown is going to attend it and offered to present it on behalf of the team).
  • 24th ICDE World Conference, Titled “Expanding Horizons – New Approaches to Open and Distance Learning (ODL)”, Bali (Indonesia), from 2 to 5 October 2011 (David Bull)

Media-based activities

  • Keep WikiResearcher updated on the project progress and activities.
  • Contribute to both international and national communities of practice through wikis and online forum discussions.
  • Provide a synopsis of the project preliminary results and outcomes to senior management executives of every Australian higher education institution by post or electronic mail, with contact details of the project team for further consultation.
  • Distribution via mailing lists of HERDSA, ASCILITE and ODLAA (potentially a total of 1,500 members) of the project preliminary results.


Phase 2

The Symposium

The symposium will be a one-day event and will take place in the first semester of stage two. It will be held in Sydney and will be facilitated by an expert with leadership experience appointed by the project team. The venue chosen for the symposium is the International School of Business and Technology (ISBT) at Wynyard, in central Sydney, which is well-located and will enable wide participation. A whole range of technology (such as wikis and twitter) will be used to assist data collection and interaction amongst participants. The symposium facilitator will explore several facilitation strategies in order to present the project findings and gather participants’ feedback through interactive and participative activities. Participants will be divided in to groups of 8 to 10 people, and their discussions will be audio-recorded. Feedback gathered from the symposium will be included in the project findings and will inform and improve the Feasibility Protocol.

Proposed Publications

  • Book Chapter (1)
  • Journal articles (1) - eg. European Journal of Open, Distance and E-learning (EURODL)

Propose Conference Presentations

  • HERDSA 2012
  • ASCILITE 2012

Media-based activities

  • Continue updating WikiResearcher on the project's progress and activities.
  • Contribute to both international and national communities of practice through wikis and online forum discussions.
  • Distribution of the final report and link to project wiki to AUQA, HERDSA, ASCILITE, EDUCAUSE, etc.
  • Provide a synopsis of project final results and outcomes to Vice-chancellors at every Australian HE institution by post or electronic mail, with contact details of the project team for further consultation, if needed.
  • Distribution via mailing lists of HERDSA, ASCILITE and ODLAA of final report and link to project wiki.
  • Send final report and Feasibility Protocol to the ALTC.


Risk Management Plan

Please click here to access the project Risk Management Plan webpage.


To do list

Items identified while developing evaluation plan.

Items identified while developing the project plan.

  • Does the project need separate lists for different audiences? Maybe not, at this stage.